July 15th 2006

The project is slightly ahead of schedule at this time. We are still on pace for a march completion date.
Next up is pouring the concrete footings.

ARCHIVE PHOTOS


August 18th, 2006

As of today we are 3 days ahead of schedule. This is the retaining wall and footings. Next week the slab will be poured
and then we should see some walls forming.

September 17th, 2006

As of today we are 5 days behind schedule. As you can see we are working on the second floor about to begin the third.
 

October 18th, 2006

As of today we are 9 days behind schedule. We are about to pour the 4th floor. Soon we will begin construction on the roof
system.


December 28th, 2006

As of today we are 11 days behind schedule. We are now dried in and our seawall is complete. We are beginning to hang sheetrock and build docks.

February 10th, 2007

We are now being told that we will be completed  by April 15th. Next up is the swimming pool and interior finishes.

March 10th, 2007

We are still planning on getting our C/O's  by April 15th. More interior finishes, Exterior painting and Parking lot are next.

March 30th, 2007

First Model Unit is complete.






 

May 3rd, 2007

Pool is complete.






 

May 10th, 2007

Building is completed and we are working on punch list and final landscaping.





 

All reservations are non-refundable with exception of non-performance by The Overlook Development
Group, LLC. All units must be closed within 30 days of completion of construction. Reservation proceeds may
be used for construction related expense. All renderings and floor plans may vary from actual finished product.
NEED NOT BE BUILT